Standard work hours for project construction are Monday - Friday, 7:00 a.m. to 5:00 p.m. Some select, less intensive activities have needed to occur on Saturdays from 8:00 a.m. to 5:00 p.m. Extended hours are also sometimes required for select activities. The contractor continues to work to keep these instances to a minimum and abutters are notified in advance.
Check back here for weekly construction updates for 421 Park Drive. If you have any questions or concerns, please contact us at construction@421parkdr.com.
The contractor will be doing some necessary sealant work on the Park Drive garage ramp, starting on Friday, November 20, through Sunday morning, November 22. The sealant work is a full multi-day process, and it requires closing access to the garage from Park Drive from 7am on Friday to 8am on Sunday. The garage will still be accessible from Fullerton Street during this time. The work will be taking place down inside the ramp, so it won’t be visible to neighbors, and it is not a noisy process.
Also this weekend, pending the successful completion of the garage ramp sealant work by 8am on Sunday, the contractor will be striping Fullerton Street on Sunday, November 22, during the day. One drive lane will always be available on Fullerton Street to allow vehicles to pass during the work. A police detail will be requested to assist with traffic management and signage will be posted. Striping is typically quiet work.
Both hardscape and streetscape work remains ongoing on Fullerton Street in coordination with the City of Boston. The street was milled on Saturday, October 24, and paved on Saturday, October 31. Work is scheduled to continue on Fullerton Street through December, with the concrete sidewalk being poured the week of December 21, depending on weather.
On weekdays, punch list work continues throughout the interior of the 421 Park Drive building and around the exterior largely inside the site fence. Crews will be sealing pavers in front of the new building on Thursday and Friday, November 19 and 20.
As a reminder, the MBTA is planning around the clock work on the tracks adjacent to 421 Park Drive on December 4 through 7. The crew will be accessing the area from Fullerton Street. This work is not related to 421 Park Drive.
Aberdeen Street Improvement Project Update
On Aberdeen Street, the contractor has installed the guardrail, wooden fence, and planters at the end of the street adjacent to the MBTA tracks in coordination with the MBTA. A crew will be installing a trellis in this location one day next week.
The new streetlights have been installed and energized. The contractor is working with Mass Bay, and they are coordinating with Eversource to de-energize the old light poles, after which the old light poles will be removed. Timing on that work is to be determined. Parking is now fully available along the right side of the road.
There won’t be any work at 421 Park or on Fullerton Street this weekend.
Both hardscape and streetscape work have been taking place on Fullerton Street in coordination with the City of Boston. The street was milled on Saturday, October 24, and paved on Saturday, October 31. Last week, crews poured new ADA sidewalk panels in several locations. The contractor is planning to stripe Fullerton Street one day next week. The exact date is TBD. The work will take place after regular hours, and one lane will always be available on Fullerton to allow vehicles to pass during the work. A police detail will be requested to assist with traffic management. Striping is typically quiet work. Work is scheduled to continue on Fullerton Street through December, with the concrete sidewalk being poured the week of December 21, depending on weather.
On weekdays, punch list work continues throughout the interior of the 421 Park Drive building and around the exterior largely inside the site fence.
The contractor needs to do some sealant work on the Park Drive garage ramp. This work is now scheduled for Friday, November 20, through Monday, November 23, and will require them to close the ramp on these days. The garage will still be accessible from Fullerton Street.
Aberdeen Street Improvement Project Update
On Aberdeen Street, the new streetlights have been installed and energized. The contractor is working with Mass Bay, and they are coordinating with Eversource to de-energize the old light poles, after which the old light poles will be removed. Parking is now fully available along the right side of the road.
The contractor has installed the screen fence frame and planters at the end of the street adjacent to the MBTA tracks in coordination with the MBTA. The new guardrail has been installed, and the planters have been filled with soil. Wood is scheduled to be installed either Friday or Monday, depending on the weather.
Last week, the crew prepped open areas on the sidewalks for concrete and poured concrete last Thursday. Abutters can continue to expect some intermittent noise.
Both hardscape and streetscape work have been taking place on Fullerton Street in coordination with the City of Boston. The street was milled on Saturday, October 24, and paved on Saturday, October 31. During the week of November 9, crews will continue working on Fullerton, including pouring new ADA sidewalk panels in several locations. On Monday, November 9, access to the 401 Park garage off Fullerton will be reduced by one lane to accommodate the work. The garage will remain accessible throughout the day. Also on Monday, canes and cones will be set up to create a safe walking pathway for pedestrians to accommodate the work on the new ADA panels. Signage will be in place to provide guidance. Work is scheduled to continue on Fullerton Street through December, with the concrete sidewalk being poured the week of December 21, depending on weather.
The contractor needs to do some sealant work on the Park Drive garage ramp. This work is currently scheduled for Thursday, November 12, through Saturday, November 14, possibly extending into Sunday, November 15, and will require them to close the ramp on these days. The garage will still be accessible from Fullerton Street. If weather is an issue, alternate dates for this work are November 20 through 23.
On weekdays, punch list work continues throughout the interior of the 421 Park Drive building and around the exterior largely inside the site fence.
Aberdeen Street Improvement Project Update
On Aberdeen Street, the new streetlights have been installed and energized. Mass Bay is coordinating with Eversource to de-energize the old light poles, after which the old light poles will be removed. Parking is now fully available along the right side of the road.
The contractor is working on the privacy fence and planters at the end of the street adjacent to the MBTA tracks in coordination with the MBTA. The new guardrail has been installed. The planters are on site and will be placed and filled with soil on either Friday, November 6, or Monday, November 9, depending on the weather. Also on Monday, November 9, the crew will be prepping the open areas on the sidewalk for concrete, and they will be pouring concrete on Tuesday. Abutters can expect some intermittent noise for the next week or so. Work hours will remain Monday through Friday, and the contractor will hold off on the noisier work until 8am.
Both hardscape and streetscape work have been taking place on Fullerton Street in coordination with the City of Boston. The street was milled on Saturday, October 24, and is scheduled to be paved on Saturday, October 31, during regular hours, 8am to 5pm. One lane of traffic will be maintained during paving to ensure Fullerton Street remains accessible to vehicles during the work. A police detail will be on site to help manage traffic. To support the paving work and give the asphalt time to cure properly, please note that vehicles will not be able to enter the 401 Park Drive parking garage from Fullerton Street from 8am to 5pm on Saturday, October 31. The garage entrance on Park Drive will be available to vehicles during this time.
The contractor is scheduled to stripe Fullerton Street on Monday night, November 2, depending on the weather. Again, one lane of traffic will be maintained during this work. Road striping is generally a quiet activity so abutters should not expect any noise during striping.
On weekdays, punch list work continues throughout the interior of the 421 Park Drive building and around the exterior largely inside the site fence.
The contractor needs to do some sealant work on the Park Drive garage ramp. This work is targeted for November 20 to 23 and will require them to close the ramp on these days. The garage will still be accessible from Fullerton Street.
Aberdeen Street Improvement Project Update
On Aberdeen Street, the new streetlights have been installed and energized. Mass Bay is coordinating with Eversource to de-energize the old light poles, after which the old light poles will be removed and the sidewalk on both sides of the street will be backfilled and patched with concrete. Parking is fully available along the right side of the road.
The contractor started working on the privacy fence and planters planned for the end of the street adjacent to the MBTA tracks in coordination with the MBTA. Abutters can expect some intermittent noise in this area for the next week or so. Work hours will remain Monday through Friday, and the contractor will hold off on the noisier work until 8am.
Both hardscape and streetscape work have been taking place on Fullerton Street in coordination with the City of Boston. Please note that the street is scheduled to be milled tomorrow, Saturday, October 24. This work will be done during regular hours. One lane of traffic will be maintained during milling to ensure Fullerton Street remains accessible to vehicles throughout the work. A police detail will be on site to help manage traffic. The Fullerton Street sidewalk opposite 201 Brookline and 401 Park will be closed on Monday and Tuesday, October 26-27, to allow for the sidewalk demo and concrete pour. Wheelchair ramp access on that sidewalk will remain available.
Fullerton is scheduled to be paved on either Saturday, October 31, or Saturday, November 7, weather dependent. Like with the milling, the contractor will work on half the street at a time to allow for two-way traffic in and out of Fullerton.
During the week, punch list work is ongoing throughout the interior of the 421 Park Drive building and around the exterior largely inside the site fence.
Aberdeen Street Streetscape Improvement Project
On Aberdeen Street, the utility work for the new streetlights is expected to last about one more week followed by about two weeks of work on the privacy fence and planters planned for the end of the street adjacent to the MBTA tracks. Work hours will remain Monday through Friday, and the contractor will hold off on the noisier work until 8am.
Last week on Aberdeen, the contractor set the leg bases for the new streetlights, and continued excavating across the street to make electrical connections for new light poles. All three excavated locations will be paved over. On Friday, October 23, the new light poles are expected to be delivered and installed in coordination with Mass Bay and Eversource. By the end of this week, the metal plates in the street will be removed and parking will be fully available along the right side of the road.
Beginning next week, the week of Monday, October 26, the contractor will be working with the utility company to de-energize the old light poles and energize the new lights. They will be prepping the sidewalks and backfilling and paving around the new light poles. They will also start working on the privacy fence at the end of the street. Abutters can expect some saw cutting on Monday when the guardrail gets removed, and a vacuum truck will be working at the end of the street for about two hours on Tuesday. The saw cutting and vac truck will generate some noticeable noise.
There is no work planned for this weekend at 421 Park Drive.
During the week, punch list work is ongoing throughout the interior of the building and around the exterior largely inside the site fence.
There is some hardscape and streetscape work taking place on Fullerton Street in coordination with the City of Boston. The contractor is doing some work needed to support new planting beds. They are also working on curbs to prepare to mill and pave the road. The street is now scheduled to be milled on Saturday, October 24, and paved on Saturday, October 31. This work will be done during regular hours. One lane of traffic will be maintained during both the milling and paving to ensure Fullerton Street remains accessible to vehicles throughout the work.
The streetscape improvement work on Aberdeen Street that began in mid-September is ongoing. The utility work for the new streetlights is expected to last about two more weeks followed by about two weeks of work on the privacy fence and planters. Work hours are Monday through Friday and the contractor will hold off on the noisier work until 8am.
This past week, the contractor set the leg bases for the new streetlights, started excavating across the street in the two of the three locations to make electrical connections for new light poles. When necessary, ‘no parking’ signs will be placed along the curb where these cuts are being made, taking one or two parking spaces offline in these locations during the work. We appreciate your attention to these signs.
Beginning the week of Monday, October 19, the contractor plans to make the third street cut, install piping, backfill the excavated areas, and pave them over with asphalt. The new light poles are expected to be installed sometime next week in coordination with Mass Bay and Eversource, after which the old light poles will be de-energized and new lights will be energized. Finally, the contractor will prep the sidewalks, and will backfill and pave around the new light poles.
There is no work scheduled on site this weekend, and there will be no work on Monday, October 12, in and around 421 Park Drive due to the holiday.
Punchlist work is ongoing throughout the interior of the building and around the exterior largely inside the site fence.
There is some hardscape and streetscape work taking place on Fullerton Street in coordination with the City of Boston. The street is currently scheduled to be paved on Saturdays, October 17 and 24. The contractor is doing the work needed to support some new planting beds. More details and dates will be shared once they become available.
The streetscape improvement work on Aberdeen Street that began in mid-September is progressing well. As a reminder, planned improvements include replacement of the existing streetlights, the addition of at least one new streetlight, and installation of some raised planter boxes and a privacy fence at the end of the street that abuts the MBTA tracks. The utility work for the streetlights is expected to last a few more weeks followed by about two weeks of work on the privacy fence and planters. Work hours are Monday through Friday and, going forward, the contractor will hold off on the noisier work until 8am.
As of Friday, October 9, the trench extending from approximately 7 to 21 Aberdeen has been backfilled with soil and paved. Now street parking is now available in front of 7 to 21 Aberdeen Street. Next, starting on Tuesday, October 13, the contractor will start cutting across the street from curb to curb in three locations. Vehicles will be able to get up and down the street during this work. Some parking spaces will need to come offline temporarily in each of the three locations. Signs will be posted. A police detail has been requested to support the work and assist with traffic. When a detail cannot be filled, the laborers will help guide vehicles needing access to Aberdeen, including the garbage trucks. Neighbors can expect some noticeable noise during work hours, particularly during the excavation portion of the work. Saw cutting and jack hammering will create some noticeable intermittent noise. The properties on Aberdeen Street are being notified separately about the work plans and impacts to the street. There will be no work on Aberdeen Street on Monday, October 12, due to the holiday.
The contractor will be working on Saturday, October 3, between REI and 401 Park Drive forming the sidewalk in preparation for plans to pour the sidewalk on Monday, October 5.
The fence line in front of 421 Park Drive has shifted to allow for more accessibility for pedestrians and cyclists. Punchlist work is ongoing throughout the interior of the building and around the exterior largely inside the site fence.
There is some hardscape and streetscape work taking place on Fullerton Street in coordination with the City of Boston. The street is scheduled to be milled and paved in the October/November timeframe. The contractor is doing the work needed to support some new planting beds. More details and dates will be shared once they become available.
A landscape contractor began the initial phase of streetscape improvement work on Aberdeen Street in mid-September, and the work has been progressing towards Beacon Street. Planned improvements include replacement of the existing streetlights, the addition of at least one new streetlight, and installation of some raised planter boxes and a privacy fence at the end of the street that abuts the MBTA tracks. The utility work for the streetlights is expected to last approximately six weeks followed by about two weeks of work on the privacy fence and planters. Work hours are Monday through Friday from 7:00 am to 3:30 pm. The contractor is setting up and coning off work areas in the street in sections along the curb line so the contractor can excavate and create a trench for new electrical conduit to support the new light poles. Street parking spaces are coming offline temporarily to accommodate each of these work areas as the contractor makes their way up the street.
As of last Wednesday, September 30, the trench extending from approximately 7 to 21 Aberdeen had been backfilled with soil, and the contractor moved the work area down the street, setting up the next and final section along the curb line close to the corner of Aberdeen and Beacon Streets. About four street parking spaces in this area had to come offline. Street parking is now available in front of 7 to 21 Aberdeen Street. A police detail has been requested to support the work and assist with traffic. When a detail cannot be filled, the laborers will help guide vehicles needing access to Aberdeen, including the garbage trucks. Neighbors can expect some noticeable noise during work hours, particularly during the excavation portion of the work. The properties on Aberdeen Street are being notified separately about the work plans and impacts to the street.
No work will occur over the weekend.
The fence line in front of 421 Park Drive has shifted to allow for more accessibility for pedestrians and cyclists. The contractor continues working in front of REI through September to perform some sidewalk and curb replacement work.
New sidewalks are being poured between the 421 and 401 Park Drive buildings. The contractor will also be installing bike racks in between the 421 Park and 401 Park buildings.
Punchlist work is ongoing throughout the interior of the building and around the exterior largely inside the site fence.
There will be some future work taking place on Fullerton Street in coordination with the City of Boston. This work is expected to begin this month. In October, the street will be milled and paved. Details and dates will be shared once they become available.
On Monday, September 14, a landscape contractor began the initial phase of streetscape improvement work on Aberdeen Street, and the work is progressing towards Beacon Street. Planned improvements include replacement of the existing streetlights, the addition of at least one new streetlight, and installation of some raised planter boxes and a privacy fence at the end of the street that abuts the MBTA tracks. The utility work for the streetlights is expected to last approximately six weeks followed by about two weeks of work on the privacy fence and planters. Work hours are Monday through Friday from 7:00 am to 3:30 pm. The contractor has set up and coned off work areas in the street in sections along the curbline so the contractor can excavate and create a trench for new electrical conduit to support the new light poles. Street parking spaces need to come offline temporarily to accommodate each of these work areas as the contractor makes their way up the street. By Monday, September 28, the existing trench in the middle of the street will be backfilled with soil, and the contractor will shift the work area down the street, setting up the next and final section along the curbline close to the corner of Aberdeen and Beacon Streets. Paving will take place on Monday at the train track end of the street, with parking in that area to be turned over after completion. Signage will be posted to provide guidance and walking detours as needed. A police detail has been requested to support the work and assist with traffic. When a detail cannot be filled, the laborers will help guide vehicles needing access to Aberdeen, including the garbage trucks. Neighbors can expect some noticeable noise during work hours, particularly during the excavation portion of the work from the sound of the excavator and safety alarms, and when the contractor is using a vacuum truck to expose underground utilities. The properties on Aberdeen Street are being notified separately about the work plans and impacts to the street.
On Saturday, September 19, work will be taking place on the underground garage ramp from 8am to 3pm. Please note that the garage ramp on the Park Drive side of the building will need to be closed on Saturday and some parking spaces will need to be taken offline during these hours to facilitate this work. The garage will still be accessible on Saturday from the Fullerton Street entrance. Work will take place on Sunday as well.
The fence line in front of 421 Park Drive has shifted to allow for more accessibility for pedestrians and cyclists. The contractor continues working in front of REI through September to perform some sidewalk and curb replacement work.
New sidewalks are being poured between the 421 and 401 Park Drive buildings. The contractor will also be installing bike racks in between the 421 Park and 401 Park buildings.
Punchlist work is ongoing throughout the interior of the building and around the exterior largely inside the site fence.
There will be some future work taking place on Fullerton Street in coordination with the City of Boston. This work is expected to begin this month. In October, the street will be milled and paved. Details and dates will be shared once they become available.
On Monday, September 14, a landscape contractor began the initial phase of streetscape improvement work on Aberdeen Street, and the work is progressing on schedule. Planned improvements include replacement of the existing streetlights, the addition of at least one new streetlight, and installation of some raised planter boxes and a privacy fence at the end of the street that abuts the MBTA tracks. The utility work for the streetlights is expected to last approximately six weeks followed by about two weeks of work on the privacy fence and planters. Work hours are Monday through Friday from 7:00 am to 3:30 pm. The contractor is setting up and coning off work areas in the street in sections along the curbline so the contractor can excavate and create a trench for new electrical conduit to support the new light poles. Street parking spaces need to come offline temporarily to accommodate each of these work areas as the contractor makes their way up the street. By Monday, September 21, the existing trench at the far end of the street will be backfilled with soil, and the contractor will shift the work area down the street, setting up the next section along the curbline roughly midway on Aberdeen between the end of the road and Beacon Street. Signage will be posted to provide guidance and walking detours as needed. A police detail has been requested to support the work and assist with traffic. When a detail cannot be filled, the laborers will help guide vehicles needing access to Aberdeen, including the garbage trucks. Neighbors can expect some noticeable noise during work hours, particularly during the excavation portion of the work from the sound of the excavator and safety alarms, and when the contractor is using a vacuum truck to expose underground utilities. The properties on Aberdeen Street are being notified separately about the work plans and impacts to the street.
There is no work planned on site this weekend.
The fence line in front of 421 Park Drive has shifted to allow for more accessibility for pedestrians and cyclists.
The contractor is working in front of REI through September to perform some sidewalk and curb replacement work.
New sidewalks are being poured between the 421 and 401 Park Drive buildings. The contractor will also be installing bike racks in between the 421 Park and 401 Park buildings.
Punchlist work is ongoing throughout the interior of the building and around the exterior largely inside the site fence.
There will be some future work on Fullerton Street in coordination with the City of Boston. This work is expected to begin in September.
Beginning next week, Monday, September 14, the contractor will begin some streetscape improvement work on Aberdeen Street, including replacement of the existing streetlights and adding at least one new streetlight along with some planters and a privacy fence at the end of the street that abuts the MBTA tracks. The work will last for approximately eight weeks, and work hours will be Monday through Friday from 7:00 am to 3:30 pm. They can expect some temporary impacts to parking spaces and sidewalk access during the work. Signage will be posted to provide guidance and walking detours. Neighbors can expect some noticeable noise, particularly during the excavation portion of the work, and when the contractor is using a vacuum truck to expose underground utilities. Aberdeen Street residents have been notified separately about the work plans and impacts to the street.
On September 17, 18, and 19, work will be taking place on the underground garage ramp. On Thursday and Friday, the 17th and 18th, work will take place lane by lane beginning at 7am, keeping the garage accessible on both days, however, on Saturday, the 19th, the garage ramp will need to be closed. Saturday work will begin at 8am.
There is no work scheduled on site this weekend or on Monday, September 7 due to the Labor Day holiday.
The fence line out in front of the building continues to shift and is being removed in sections to allow for more accessibility for pedestrians and cyclists.
The contractor will be working in front of REI through mid-September to perform some sidewalk and curb replacement work.
New sidewalks will be poured between the 421 and 401 Park Drive buildings. The contractor will also be installing bike racks in between the 421 Park and 401 Park buildings.
Punchlist work is ongoing throughout the interior of the building and around the exterior inside the site fence.
There will be some future work on Fullerton Street in coordination with the City of Boston. This work is expected to begin later in September.
Beginning on Monday, September 14, the contractor will begin some streetscape improvement work on Aberdeen Street, including replacement of the existing streetlights and adding at least one new streetlight along with some planters and a privacy fence at the end of the street that abuts the MBTA tracks. The work will last for approximately eight weeks, and work hours will be Monday through Friday from 7:00 am to 3:30 pm. They can expect some temporary impacts to parking spaces and sidewalk access during the work. Signage will be posted to provide guidance and walking detours. Neighbors can expect some noticeable noise, particularly during the excavation portion of the work, and when the contractor is using a vacuum truck to expose underground utilities. Aberdeen Street residents are being notified separately about the work plans and impacts.
There is no work scheduled on site this weekend.
The contractor will be working in front of REI through mid-September to perform some sidewalk and curb replacement work.
The fence line out in front of the building continues to shift and is being removed in sections to allow for more accessibility for pedestrians and cyclists.
Next week, the contractor will be installing a topcoat of asphalt at the two MBTA gates located on the walkway alongside the building. They will also be installing bike racks in between the 421 Park and 401 Park buildings.
The pathway closest to the building has been asphalted, and will remain closed to pedestrians for the time being. New sidewalks have been poured between the 421 and 401 Park Drive buildings.
Punchlist work is ongoing throughout the interior of the building and around the exterior.
There will be some future work on Fullerton Street in coordination with the City of Boston. This work is expected to begin in September.
In mid-September, the contractor will begin some streetscape work on Aberdeen Street, including replacement of the existing streetlights and adding at least one new streetlight along with some planters and a privacy fence at the end of the street that abuts the MBTA tracks. More information will be provided as the start date for that work gets closer.
There won’t be any work on site this coming weekend at 421 Park Drive.
The fence line out in front of the building has been shifting and removed in sections over the last several weeks to allow for more accessibility for pedestrians and cyclists. This month, the majority of the fencing will be removed, making the area fully accessible.
The pathway closest to the building has been asphalted, and will remain closed to pedestrians for the time being. Next week, the contractor will be pouring the remaining sidewalks between the 421 and 401 Park Drive buildings and the walkway space is needed to support this work.
Beginning next week, through mid-September, the contractor will be installing a site fence in front of REI to perform some sidewalk and curb replacement work.
At the south jump lobby, swing staging is in place so workers can install brick on the east façade. Scaffolding will stay up this month to support grating installation, which is scheduled for next week.
Punchlist work is ongoing throughout the interior of the building and around the exterior.
There will be some future work on Fullerton Street in coordination with the City of Boston. This work is expected to begin in the fall.
In September, the contractor will begin some streetscape work on Aberdeen Street, including replacement of the existing streetlights and adding at least one new streetlight along with some planters and a privacy fence at the end of the street that abuts the MBTA tracks. More information will be provided as the start date for that work gets closer.
There will be no work on site at 421 Park Drive over this coming weekend.
The fence line out in front of the building has been shifting and removed over the last several weeks to allow for more accessibility for pedestrians and cyclists. This month, the majority of the fencing will be removed, and the area will be fully accessible.
The pathway closest to the building is being asphalted and re-opened to pedestrians by this weekend.
Beginning on Monday, August 24, through mid-September, the contractor will be installing a site fence in front of REI to perform some sidewalk and curb work.
At the south jump lobby, the contractor has been using swing staging to install brick on the east façade. The scaffolding will stay up this month to support grating installation, which is scheduled for next week. The water testing on south jump lobby east wall is complete.
There will be some future work on Fullerton Street in coordination with the City of Boston. This work is expected to begin in the fall.
At the end of this month, the contractor will begin some streetscape work on Aberdeen Street, including replacement of the existing streetlights and adding at least one new streetlight along with some planters and a privacy wall at the end of the street that abuts 421 Park Drive. More information will be provided as the start date for that work gets closer.
There will be no work on site at 421 Park Drive over this coming weekend.
The fence line out in front of the building has been shifting and removed over the last several weeks to allow for more accessibility for pedestrians and cyclists. This month, the majority of the fencing will be removed, and the area will be fully accessible.
The pathway closest to the building will be asphalted and re-opened to pedestrians by the middle of next week. For now, pedestrians should use the new multi-use MBTA walkway.
The contractor has installed a temporary fence around a small area on the front of the building so they can remove the temporary asphalt, connect the irrigation line, backfill, and place the permanent asphalt and sidewalk. From approximately mid-August to mid-September, the contractor will be installing a site fence in front of REI to perform some sidewalk and curb work.
On the MBTA path side of the building (West Road), the contractor has replaced the pavers, including those located at the end section of the MBTA path where it connects to the 421 Park pathway at the front of the building.
At the south jump lobby, the contractor has been using swing staging to install brick on the east façade. The scaffolding will stay up this month to support grating installation, which is scheduled for mid-month. The contractor will be performing some water testing on south jump lobby east wall next week.
There will be some future work on Fullerton Street in coordination with the City of Boston. This work is expected to begin in the fall.
We use cookies to analyze website traffic and optimize your website experience. By accepting our use of cookies, your data will be aggregated with all other user data.