Standard work hours for project construction are Monday - Friday, 7:00 a.m. to 5:00 p.m. Some select, less intensive activities may need to occur on Saturdays from 8:00 a.m. to 5:00 p.m. Extended hours may be required for select activities. The contractor will strive to keep these instances to a minimum and abutters will be notified in advance.
Check back here for upcoming construction updates for 421 Park Drive. If you have any questions or concerns, please contact us at construction@421parkdr.com.
Work at 421 Park Drive will continue to take place on various levels inside the building on Saturdays for the foreseeable future, including this Saturday, March 29. Neighbors can expect to see crew members on site and hear some work taking place on Saturdays.
Separate from the 421 Park Drive project, the property owner of 401 Park Drive will have a crane in operation out in front of their building on Saturday, March 29, for one day to access the building’s upper levels.
Interior work is continuing on all levels on weekdays during regular work hours. The contractor will be pouring the next concrete slab inside the excavated area on one day later next week. On this day, concrete pump trucks will be arriving on site at 6:00 a.m. to be ready for concrete arrival at 7:00 a.m. Backup alarms should not be an issue at 6:00 a.m. as the trucks will be pulling in, not backing up.
Work inside the excavated area is ongoing. Over the next several weeks, the contractor will be working on building the garage columns and will be removing the wall bracing in phases.
The new Beacon Street crosswalk at Miner Street can move forward once Eversource makes its necessary electrical connections, after which the area will be restriped. The neighborhood’s ongoing patience with this project is appreciated.
Work at 421 Park Drive continues to take place on various levels inside the building on Saturdays for the foreseeable future, including this Saturday, March 22. The hoist will not be used on Saturday unless needed in the event of an emergency. Crews will be lowering decking material into the excavation on Saturday too, however, most of the materials are already onsite, so truck traffic will be minimal. Neighbors can expect to see crew members on site and hear some work taking place on Saturdays. Interior work is continuing on all levels on weekdays during regular hours as well.
The contractor poured the first of several concrete slabs inside the excavated area at the front of the building last Saturday. The project team appreciates the neighborhood’s patience during this necessary work. The next two concrete slab pours are scheduled for Wednesday, March 26, and Friday, March 28. On these days, concrete pump trucks will be arriving on site at 6:00 a.m. to be ready for concrete arrival at 7:00 a.m. Backup alarms should not be an issue at 6:00 a.m. as the trucks will be pulling in, not backing up.
Work inside the excavated area is ongoing. Over the next several weeks, the contractor will be working on building the garage columns and will be removing the wall bracing in phases.
Waterproofing on the building’s 6th floor is now complete. There will be a crane operating adjacent to the building at the end of Fullerton Street next week on Tuesday and Wednesday, March 25 and 26, between 7:00 a.m. and 5:00 p.m. Delivery vehicles will have full access to the loading dock during this work and access to Fullerton Street will be maintained for other vehicles.
The project team will continue to follow up with Eversource to expedite the completion of the new Beacon Street crosswalk at Miner Street. The crosswalk can move forward once Eversource makes its necessary electrical connections, after which the area will be restriped. The neighborhood’s ongoing patience with this project is appreciated.
Work at 421 Park Drive continues to take place on various levels inside the building on Saturdays for the foreseeable future, including this Saturday, March 15. The hoist will not be used on Saturday unless needed in the event of an emergency.
Because of some inclement weather forecasted early next week and other factors, the contractor will need to pour the first of several concrete slabs in the excavated area in front of the building on Saturday, March 15. Unfortunately, this work cannot be done when there is the threat of rain. Because of its size, this pour, from start to finish, will take about 12 hours. As such, this work on Saturday is currently scheduled to begin at 7:00 a.m. with concrete pump trucks arriving on site to set up at 6:00 a.m. to be ready for concrete arrival at 7:00 a.m. Backup alarms should not be an issue as the trucks will be pulling in, not backing up. The finishing work that needs to take place will last until about 7:00 p.m. on Saturday, however, this work will be taking place 30 feet down inside the excavated area and should not be noticed by the community. The project team appreciates the neighborhood’s patience during this necessary work.
Waterproofing is underway on the building’s 6th floor. Due to its location, this work needs to take place after regular hours. The contractor began this activity on Monday, March 10, in the evenings and this work is scheduled to continue on weekdays from 9:00 p.m. and 5:00 a.m. through Friday, March 21. It is not expected that there will be any noticeable noise or disruption to our neighbors during this after-hours activity.
Work inside the excavated area out in front of the building is ongoing and interior work is continuing on all levels on weekdays during regular hours.
The project team continues working to expedite the completion of the new Beacon Street crosswalk at Miner Street. The crosswalk can move forward once Eversource makes its necessary electrical connections, after which the area will be restriped. The neighborhood’s ongoing patience with this project is appreciated.
Work will continue to take place on various levels inside the building on Saturdays for the foreseeable future, including this Saturday, March 8. Trucks will not be entering/exiting the Park Drive side of the site this Saturday, however, some work will be taking place down inside excavated area during standard work hours. The hoist will not be used on Saturday unless needed in the event of an emergency.
Due to the location of some waterproofing work that needs to take place on the 6th floor of the new building, this work will need to take place after normal work hours. The contractor will be working in this location beginning on Monday, March 10, through Friday, March 21, between 9:00 p.m. and 5:00 a.m. Because of the type and location of this work, it is not expected that there will be any noticeable noise or disruption to our neighbors during this after-hours activity.
The excavation work out in front of the building is complete, but work inside the excavated area will continue. Interior work is continuing on all levels of the building as well.
The project team continues to try and expedite the completion of the new Beacon Street crosswalk at Miner Street. The crosswalk can move forward once Eversource makes its necessary electrical connections, after which the area will be restriped. The neighborhood’s ongoing patience with this project is appreciated.
Work will continue to take place on various levels inside the building on Saturdays for the foreseeable future, including this Saturday, March 1. Trucks will not be entering/exiting the Park Drive side of the site this Saturday, however, some excavation work will occur during standard work hours. The hoist will not be used on Saturday unless needed in the event of an emergency.
To complete some critical waterproofing work that needs to take place inside the excavated area on the Park Drive side of the building, a small crew of four people will need to work inside the hole on Sunday, March 2, from 8:00 a.m. to 3:00 p.m. to get this important work done. Trucks will not be entering/exiting and there will be no excavation work on Sunday. We recognize Sunday work is not ideal but, because this work will be performed 30-40 feet down inside the excavation with a team of only four people, we do not expect that there will be any noticeable noise or disruption to our neighbors.
Excavation work will continue in front of the building for about two more weeks on weekdays. Interior work is continuing on all levels of the building as well.
The project team continues working to expedite the completion of the new Beacon Street crosswalk at Miner Street. The crosswalk can move forward once Eversource makes its necessary electrical connections, after which the area will be restriped. The neighborhood’s ongoing patience with this project is appreciated.
Work will continue to take place on various levels inside the building on Saturdays for the foreseeable future. Trucks will not be entering/exiting the Park Drive side of the site this Saturday, however, some excavation work will occur during standard work hours. The hoist will not be used on Saturday unless needed in the event of an emergency.
As we have noted in our weekly updates over the last few weeks, the contractor will be bringing in a crane this weekend to hoist a generator onto the building’s roof. Because this is a sizeable undertaking that includes hours of crane assembly and disassembly, the crane sections will be arriving via Fullerton Street starting around 12 noon on Friday, February 21. Crews will be working through Friday evening and Saturday to place the generator on to the roof. During the hoist, the crane will be positioned in the northwest corner of the work site in front of the building’s loading dock. The goal is to have the crane disassembled and removed by around 9:00 p.m. on Saturday evening. If more work is required to remove the crane, work will resume on Sunday morning at 7:00 a.m. to move the crane off the job site. The project team appreciates the neighborhood’s patience with this critical piece of work.
Excavation work will continue on the Park Drive side of the new building for about two more weeks. Interior work is continuing on all levels of the building as well.
The project team is working to expedite the completion of the new Beacon Street crosswalk at Miner Street. The crosswalk can move forward once Eversource makes its necessary electrical connections, after which the area will be restriped. The neighborhood’s ongoing patience with this project is appreciated.
Work will be taking place on various levels inside the building this Saturday, February 15. Trucks will not be entering/exiting the site on Saturday, however, the contractor will be doing some excavation work during standard work hours. The hoist will not be used on Saturday unless needed in the event of an emergency. Please note the job site will be closed on Monday, February 17, in observance of Presidents’ Day.
Excavation work will continue on the Park Drive side of the new building for a few more weeks. Deliveries are arriving to the new building’s loading dock via Fullerton Street. Interior work is ongoing on all levels of the building as well.
As a reminder, over the weekend beginning Friday afternoon, February 21, the contractor will be bringing in a crane to hoist a generator onto the building’s roof. Because this is a sizeable undertaking that includes hours of crane assembly and disassembly, the crane sections will be arriving on the afternoon of Friday, the 21st, via Fullerton Street and crews will be working through Friday evening and Saturday to place the generator on to the roof. The crane will be positioned in the northwest corner of the work site in front of the building’s loading dock during the hoist. The goal is to have the crane disassembled and removed by around 9:00 p.m. on Saturday evening. If more work is required to remove the crane, work will resume on Sunday morning to move the crane off the job site. The project team appreciates the neighborhood’s patience with this critical piece of work.
The project team continues to try and expedite the completion of the new Beacon Street crosswalk at Miner Street. The crosswalk can move forward once Eversource makes its necessary electrical connections, after which the area will be restriped. The neighborhood’s ongoing patience with this project is appreciated.
This Saturday, February 8, crews will be working on various levels inside the building. Trucks will not be entering/exiting the site on Saturday, however, the contractor will be doing some excavation work during standard work hours. The hoist will not be used on Saturday unless needed in the event of an emergency.
Excavation work will continue on the Park Drive side of the new building for a few more weeks. Deliveries are arriving to the new building’s loading dock via Fullerton Street. Interior work is ongoing on all levels of the building as well.
Please note that, over the weekend beginning Friday afternoon, February 21, the contractor will be bringing in a crane to hoist a generator onto the building’s roof. Because this is a sizeable undertaking that includes hours of crane assembly and disassembly, the crane sections will be arriving on the afternoon of Friday, the 21st, via Fullerton Street and crews will be working through Friday and Saturday evenings and the weekend to get the generator placed on the roof. The crane will be positioned in the northwest corner of the work site in front of the building’s loading dock during the hoist. Crane disassembly and removal is expected to be complete by Sunday afternoon. The project team appreciates the neighborhood’s patience with this critical piece of work.
The project team continues to try and expedite the completion of the new Beacon Street crosswalk at Miner Street. The crosswalk can move forward once Eversource makes its necessary electrical connections, after which the area will be restriped. The neighborhood’s ongoing patience with this project is appreciated.
The job site will be closed on Monday, February 17, in observance of Presidents’ Day.
This Saturday, February 1, crews will be working on various levels inside the building. Trucks will not be entering/exiting the site on Saturday, however, the contractor will be doing some excavation work during standard work hours. As usual, the hoist will not be used on Saturday unless needed in the event of an emergency.
Excavation work will continue on the Park Drive side of the new building for a few more weeks. Deliveries are arriving to the new building’s loading dock via Fullerton Street. Interior work is ongoing on all levels of the building as well.
Please note that, over the weekend beginning Friday afternoon, February 21, the contractor will be bringing in a crane to hoist a generator onto the building’s roof. Because this is a sizeable undertaking that includes hours of crane assembly and disassembly, the crane sections will be arriving on Friday, the 21st, via Fullerton Street and crews will be working through Friday and Saturday evenings and the weekend to get the generator placed on the roof. The crane will be positioned in the northwest corner of the work site in front of the building’s loading dock during the hoist. Crane disassembly and removal is expected to be complete by Sunday afternoon. The project team appreciates the neighborhood’s patience with this critical piece of work.
The project team continues to try and expedite the completion of the new Beacon Street crosswalk at Miner Street. The new crosswalk can be finished once Eversource makes the necessary electrical connections, after which the area will be restriped. The neighborhood’s ongoing patience with this project is appreciated.
The job site will be closed on Monday, February 17, in observance of Presidents’ Day.
This Saturday, January 25, crews will be working on various levels inside the building. Trucks will not be entering/exiting the site on Saturday, however, the contractor will be doing some excavation work during standard work hours. As usual, the hoist will not be used on Saturday unless needed in the event of an emergency.
A few more weeks of excavation work will continue on the Park Drive side of the new building. Deliveries are arriving to the new building’s loading dock via Fullerton Street. Interior work is ongoing on all levels of the building as well.
Please note that, over the weekend beginning Friday, February 21, the contractor will be bringing in a crane to hoist a generator onto the building’s roof. Because this is a sizeable undertaking that includes hours of crane assembly and disassembly, the crane sections will be arriving on Friday, the 21st, and crews will be working through Friday and Saturday evenings and the weekend to get the generator placed on the roof. Crane disassembly and removal is expected to be complete by Sunday afternoon (February 23). The project team appreciates the neighborhood’s patience with this critical piece of work.
The new crosswalk at the intersection of Beacon Street and Miner Street will be finished once Eversource makes the necessary electrical connections, after which the area will be restriped. The project team is doing everything they can to help expedite this work with Eversource so the crosswalk can be completed. The neighborhood’s ongoing patience with this project is appreciated.
This Saturday, January 18, crews will be working on various levels inside the building. Trucks will not be entering/exiting the site on Saturday, however, the contractor will be doing some excavation work during standard work hours. The hoist will not be used on Saturday unless needed in the event of an emergency.
The job site will be open on Monday, January 20, with a limited crew.
A few more months of excavation work will continue on the Park Drive side of the new building. Deliveries are ongoing and arriving to the new building’s loading dock via Fullerton Street. Interior work is ongoing on all levels of the building as well.
Completion of the new crosswalk at the intersection of Beacon Street and Miner Street continues to hinge on Eversource making the necessary electrical connection, after which the area will be restriped. The project team is doing everything they can to help expedite this work with Eversource so the crosswalk can be finished. The neighborhood’s ongoing patience with this project is appreciated.
Crews will be working on various levels inside the building this Saturday, January 11. Trucks will not be entering/exiting the site on Saturday, however, the contractor will also be doing some excavation work during standard work hours. As usual, the hoist will not be used on Saturday unless needed in the event of an emergency.
A few more months of excavation work will continue on the Park Drive side of the new building. Deliveries will continue arriving to the new building’s loading dock via Fullerton Street and interior work is ongoing on all levels throughout the building.
Completion of the new crosswalk at the intersection of Beacon Street and Miner Street continues to hinge on Eversource making the necessary electrical connection, after which the area will be restriped. The project team is doing everything they can to help expedite this work with Eversource so the crosswalk can be finished. The neighborhood’s ongoing patience with this project is appreciated.
The job site will be open and active on Monday, January 20.
Crews will be working on various levels inside the building this Saturday, January 4. There won’t be any trucks entering/exiting the site on Saturday, however, the contractor will also be doing some excavation work during standard work hours. As usual, the hoist will not be used on Saturday unless needed in the event of an emergency.
As previously noted, a few months of excavation work will continue on the Park Drive side of the new building. Deliveries will continue arriving at the new building’s loading dock via Fullerton Street and interior work is ongoing on all levels throughout the building.
Completion of the new crosswalk at the intersection of Beacon Street and Miner Street continues to hinge on Eversource making the necessary electrical connection, after which the area will be restriped. The project team is doing everything they can to help expedite this work so the crosswalk can be finished. The neighborhood’s patience with this project is appreciated.
Crews will be working on various levels inside the building this Saturday, December 28. The contractor will also be doing some excavation work on Saturday during standard work hours. As usual, the hoist will not be used on Saturday unless needed in the event of an emergency.
A few months of excavation work will continue on the Park Drive side of the new building. Deliveries will continue arriving to the new building’s loading dock via Fullerton Street and interior work is ongoing on all levels throughout the building.
Completion of the new crosswalk at the intersection of Beacon Street and Miner Street continues to hinge on Eversource making the necessary electrical connection, after which the area will be restriped. The neighborhood’s patience with this project is appreciated. The project team is doing everything they can to help expedite this so the crosswalk can be finished.
The 421 Park Drive team wishes everyone a safe and happy New Year.
Crews will be working on various levels inside the building this Saturday, December 21. The contractor will also be using excavators on Saturday during standard work hours. The hoist will not be used on Saturday unless needed in the event of an emergency. Finally, on Saturday, the building manager at 401 Park Drive will be bringing in a crane in front of REI to perform some work on the building’s upper levels. This is a one-day operation during standard work hours. Access to REI and Timeout Market will be maintained during this work.
Work will continue for several months on the Park Drive side of the new building. Slurry wall construction is complete, and crews are now working on a few months of excavation.
The after-hours saw cutting of an exterior building wall was finished last week.
Completion of the new crosswalk at the intersection of Beacon Street and Miner Street continues to hinge on Eversource making the necessary electrical connection, after which the area will be restriped. The neighborhood’s patience with this project is appreciated.
The job site will be closed on Wednesday, December 25, for the Christmas holiday.
We use cookies to analyze website traffic and optimize your website experience. By accepting our use of cookies, your data will be aggregated with all other user data.