Standard work hours for project construction are Monday - Friday, 7:00 a.m. to 5:00 p.m. Some select, less intensive activities have needed to occur on Saturdays from 8:00 a.m. to 5:00 p.m. Extended hours are also sometimes required for select activities. The contractor continues to work to keep these instances to a minimum and abutters are notified in advance.
Check back here for weekly construction updates for 421 Park Drive. If you have any questions or concerns, please contact us at construction@421parkdr.com.
Work at 421 Park Drive is ongoing on multiple levels inside the building on weekends, including this Saturday, March 21. On the exterior of the building this Saturday, crews will be taking down the staging on the east wall of the south jump lobby, and installing brick via staging in the south courtyard.
Work on the Park Drive sidewalk is complete.
Earlier this month, the contractor opened the new multi-use walking path that connects the MBTA station to Park Drive. Located on the opposite side of the underground garage entrance ramp closer to the new building, the new path is separated from the work site on both sides by new 8-foot fencing and scrim. Clear signage is posted to provide guidance to pedestrians and cyclists. Site work in the area of the old pathway is underway, including the installation of new structural soils, light pole bases, conduits, and stone wall support this month and into April.
Out in front of the new building, workers continue to install pavers in several locations. The installation of planting soils and new plantings will follow into April and May. Work will continue to take place around the exterior canopy with the installation of the copper roof system through mid-April. The installation of exterior signage will take place later this month.
Work continues on the south jump lobby on several levels. On the jump lobby entrance canopy, workers are installing skylight glass. A crane will be in use next week to work on the skylights. Metal panels are being installed as well into April.
Interior work continues on all levels on weekdays during regular work hours. Work on the west and south balconies and the east terrace continues as well.
Work continues on the MBTA path side of the building as well with the installation of lighting followed by soils in April. Granite curbing is being installed this month as well followed by as asphalt paver base and then pavers. The temporary fence along this path will remain in its current location until the landscaping work is completed.
Activity on the Atrius Health garage side of the job site is ongoing. Fence posts will be installed later in April, and new fencing is scheduled for installation later this year.
Work at 421 Park Drive is ongoing on multiple levels inside the building on weekends, including this Saturday and Sunday, March 14 and 15. On Saturday, crews will be making changes to the building’s staging and installing tube support posts. On both days this weekend, crews will be working on the entrance canopy roofing.
The contractor opened the new multi-use walking path that connects the MBTA station to Park Drive on March 2. The new path is located on the opposite side of the underground garage entrance ramp closer to the new building and is separated from the work site on both sides by new 8-foot fencing and scrim. Clear signage is posted to provide guidance to pedestrians and cyclists. Site work in the area of the old pathway is underway, including the installation of new structural soils and stone wall support in March and April.
Please note that a subcontractor will continue working on the sidewalk on Park Drive removing soils through Tuesday, March 17. With this sidewalk closed, new signs are directing pedestrians to cross Park Drive prior to the work zone and use the opposite sidewalk.
Out in front of the new building, workers continue to install pavers in several locations out front for the next week or so. The installation of planting soils and new plantings will follow into April and May. Work will continue to take place around the exterior canopy with the installation of metal panels, lighting, and the copper roof system. A crane will be in use next week to work on the skylights for the jump lobby entrance canopy. The installation of exterior signage will take place later this month.
Work continues on the south jump lobby on several levels. On the jump lobby entrance canopy, workers are installing skylight frames and glass. Metal panels are being installed as well into March.
Interior work continues on all levels on weekdays during regular work hours. Work on the west and south balconies and the east terrace continues as well.
Work continues on the MBTA path side of the building as well with the installation of lighting followed by soils in April. Granite curbing is being installed this month as well followed by as asphalt paver base and then pavers. The temporary fence along this path will remain in its current location until the landscaping work is completed.
Activity on the Atrius Health garage side of the job site is ongoing. Fence posts will be installed later in early April, and new fencing is scheduled for installation later this year.
Work at 421 Park Drive is ongoing on multiple levels inside the building on Saturdays, including this Saturday, March 7. Also this weekend on the outside of the building, paver work will be taking place on Saturday and Sunday, March 7 and 8, along with some work on the entrance canopy and the west balcony. And, a crew will also be on site on both days this weekend to remove the north stair tower at level four.
Snow removal continues around the job site, including after hours when necessary.
The contractor opened the new multi-use walking path that connects the MBTA station to Park Drive on Monday, March 2. The new path is located on the opposite side of the underground garage entrance ramp closer to the new building and is separated from the work site on both sides by new 8-foot fencing and scrim. Clear signage is posted to provide guidance to pedestrians and cyclists. Site work in the area of the old pathway will follow, including the installation of new structural soils and stone wall support in March and April.
Please note that a subcontractor will be working on the sidewalk on Park Drive from Monday, March 9, through Tuesday, March 17, removing soils. With this sidewalk closed, pedestrians will be directed via signage to cross the road prior to the work zone and use the sidewalk on the opposite side of Park Drive.
Work continues on the south jump lobby on several levels. On the jump lobby entrance canopy, workers are installing skylight frames and glass. Metal panels are being installed as well into March.
Interior work continues on all levels on weekdays during regular work hours. Work on the west and south balconies and the east terrace continues as well.
Work continues on the MBTA path side of the building as well with the installation of lighting followed by soils in April. Granite curbing will be installed this month as well followed by as asphalt paver base and then pavers. The temporary fence along this path will remain in its current location until the landscaping work is completed.
On the front of the new building, workers continue to install pavers in several locations out front for the next few weeks. Work will continue to take place around the exterior canopy with the installation of metal panels, lighting, and the copper roof system. A crane will be in use next week to work on the skylights for the canopy. The installation of exterior signage will take place this month.
Activity on the Atrius Health garage side of the job site is ongoing. Fence posts will be installed later in March, and new fencing is scheduled for installation later this year.
Work at 421 Park Drive is ongoing on multiple levels inside the building on Saturdays, including this Saturday, February 28. Also on Saturday on the outside of the building, paver work will be taking place along with some work on the south jump lobby canopy roof and on swing staging on the upper floors of the south elevation.
Snow removal continues around the job site, including after hours when necessary.
Due to the recent snowstorms, the opening of the new multi-use walking path that connects the MBTA station to Park Drive was postponed. A new opening date is imminent. The new path is located on the opposite side of the underground garage entrance ramp closer to the new building. Before the path opens, clear signage will be posted to provide guidance to pedestrians and cyclists. Site work in the area of the old pathway will follow, including the installation of new structural soils in March.
Work continues on the south jump lobby on several levels. On the jump lobby entrance canopy, workers are installing skylight frames and glass. Metal panels are being installed as well into March.
Interior work continues on all levels on weekdays during regular work hours. Work on the west and south balconies and the east terrace continues as well.
Work continues on the MBTA path side of the building as well with the installation of pavers and lighting. The temporary fence along this path will remain in its current location until the landscaping work is completed.
On the front of the new building, tenting is in place in some areas and workers are installing pavers in several locations out front into March. Work will continue to take place around the exterior canopy with the installation of metal panels, lighting, and the copper roof system. The installation of exterior signage will take place in March.
Activity on the Atrius Health garage side of the job site is ongoing. Fence posts will be installed in mid-March, and new fencing is scheduled for installation later this year.
Work at 421 Park Drive is ongoing on multiple levels inside the building on Saturdays, including this Saturday, February 21. Also this weekend, paver work will be taking place on both Saturday and Sunday along with some work on the south jump lobby canopy roofing.
Snow removal continues around the job site and may continue Sunday into Monday morning given the current forecast.
On Tuesday, February 24, at 6:00 a.m. the contractor is scheduled to open the new multi-use walking path that connects the MBTA station to Park Drive. The new path is located on the opposite side of the underground garage entrance ramp closer to the new building. Clear signage will be posted to provide guidance to pedestrians and cyclists. Site work in the area of the old pathway will follow, including the installation of new structural soils in early March.
Work continues on the south jump lobby on several levels. On the jump lobby entrance canopy, workers are installing skylight frames with glass installation starting next week using a crane. Metal panels will also be installed starting next week into March.
Interior work continues on all levels on weekdays during regular work hours. Work on the west and south balconies and the east terrace continues as well.
Work is progressing on the MBTA path side of the building as well, and the area is being prepped for pavers and lighting. The temporary fence along this path will remain in its current location until the landscaping work is completed.
On the front of the building, tenting is in place in the canopy area and workers are installing pavers in several areas out front through February. Work will continue to take place around the exterior canopy with the installation of metal panels followed by lighting and the copper roof system. The installation of exterior signage will take place in March.
Activity on the Atrius Health garage side of the job site is ongoing. Fence posts are being installed starting early March and new fencing is scheduled for installation later this year.
Work is ongoing on multiple levels inside 421 Park Drive on Saturdays, including Saturday, February 14. Also this weekend, paver work will be taking place on both Saturday and Sunday along with some work on the canopy and lobby roof. The job site will be open on Monday, February 16, with a light crew in place continuing work on the pavers, canopy, and lobby roof.
Snow removal continues around the job site. Work continues on the south jump lobby on several levels and around the Star Market canopy, including metal panel and brick façade installation, and pavers below the canopy. On the jump lobby entrance canopy, workers are installing framing, roofing, panels and lighting with skylight glass being installed starting next week.
Interior work continues on all levels on weekdays during regular work hours. Work on the west and south balconies and the east terrace continues as well.
Work is progressing on the MBTA path side of the building as well, and the area is being prepped for pavers and lighting. The temporary fence along this path will remain in its current location until the landscaping work is completed.
On the front of the building, some tenting is being added to right of the canopy area and workers are installing pavers in several areas through February. Crews are staging for planter installation and are installing temporary asphalt, fencing and lights for the new pedestrian walkway next week. Work will continue to take place around the exterior canopy with waterproofing, copper roof system, and lighting installation. Below the canopy, curbing is being installed along with ADA sidewalk ramps. The installation of exterior signage will take place in early March.
On Tuesday, February 24, at 6:00 a.m. the contractor is scheduled to open the new multi-use walking path that connects the MBTA station to Park Drive. The new path will be located on the opposite side of the underground garage entrance ramp closer to the new building. Clear signage will be posted to provide guidance to pedestrians and cyclists. Site work in the area of the old pathway will follow.
Activity on the Atrius Health garage side of the job site is ongoing. Fence posts are being installed in March. New fencing is scheduled for installation later this year.
Work is ongoing on multiple levels inside 421 Park Drive on Saturdays, including Saturday, February 7. Also this Saturday, landscaping work will be taking place at the southern portion of the site as well as framing and metal panel work at the south jump lobby. A crane will also be positioned and in use on the Park Drive side of the building, both this Saturday and next, February 7 and 14, to hoist materials onto the south jump lobby balconies and roof area.
Snow removal continues around the job site. Work continues on the south jump lobby on several levels and around the Star Market canopy, including lighting, waterproofing, metal panel installation, and pavers below the canopy. On the jump lobby entrance canopy, workers are installing framing, roofing, panels and lighting with skylight glass coming in mid-February.
Interior work continues on all levels on weekdays during regular work hours. Work on the west and south balconies and the east terrace is progressing.
Work is progressing on the MBTA path side of the building as well, and the area is being prepped for pavers. Lights are being installed as well. The temporary fence along this path will remain in its current location until the landscaping work is completed.
On the front of the building, some tenting is being added to right of the canopy area and workers are installing pavers in several areas through February. Crews are staging for planter installation and will be installing temporary, asphalt, fencing and lights at the pedestrian walkway. Work will continue to take place around the exterior canopy with waterproofing, copper roof system, and lighting installation. Below the canopy, curbing is being installed along with ADA sidewalk ramps. The installation of exterior signage will take place in early March.
Later in February, the multi-use walking path connecting the MBTA station to Park Drive will be temporarily repositioned closer to the new building. More details will be provided as that shift gets closer.
Activity on the Atrius Health garage side of the job site is ongoing. Fence posts are being installed now in March. New fencing is scheduled for installation later this year.
Work is ongoing on multiple levels inside 421 Park Drive on Saturdays, including Saturday, January 31. Also this Saturday, landscaping work will also be taking place at the southern portion of the site as well as framing and metal panel work at the south jump lobby. Crews will also be prepping the site for the impending snow fall. On Sunday into Monday, the contractor will likely be plowing and removing snow on site. Neighbors may notice an increased presence of snow removal equipment and trucks as a result.
On weekdays, snow removal continues around the job site. Work continues on the south jump lobby on several levels and around the Star Market canopy, including lighting, waterproofing, metal panel installation, and pavers below the canopy. On the jump lobby entrance canopy, workers are installing framing, roofing, panels and lighting with skylight glass coming in mid-February.
Interior work continues on all levels on weekdays during regular work hours. Work on the west and south balconies and the east terrace is progressing.
Work is progressing on the MBTA path side of the building as well, and the area is being prepped for pavers. The temporary fence along this path will remain in its current location until the landscaping work is completed.
On the front of the building, concrete placements are complete. Snow removal will continue. Some tenting is being added to right of the canopy area and workers are installing pavers in several areas through February. Crews are staging for planter installation and installing conduit for light poles, drainage piping, soil, aeration lines, planting beds, lighting, and curbing along with crushed stone, lighting pathways, and benches. Work will continue to take place around the exterior canopy with waterproofing, copper roof system, and lighting installation. Below the canopy, curbing is being installed along with ADA sidewalk ramps. The installation of exterior signage will take place in early March.
Later in February, the multi-use walking path connecting the MBTA station to Park Drive will be repositioned closer to the new building. More details will be provided as the date gets closer.
Activity on the Atrius Health garage side of the job site is ongoing. Fence posts are being installed into early February along with lighting conduit. New fencing is scheduled for installation early this year.
Work continues on multiple levels inside 421 Park Drive on Saturdays, including Saturday, January 24. Also this Saturday, landscaping work will also be taking place at the southern portion of the site as well as framing and metal panel work at the south jump lobby. Crews will also be prepping the site for the impending snowstorm. On Sunday into Monday, the contractor will be plowing and removing snow on site. Neighbors may notice an increased presence of snow removal equipment and trucks as a result.
On weekdays, work continues at the front of the building for the underground garage entrance ramp, including installation of pavers, ramp wall light fixtures, and ramp signage. Work continues on the south jump lobby on several levels and around the Star Market canopy, including lighting, waterproofing, metal panel installation, and pavers below the canopy. On the jump lobby entrance canopy, workers are installing framing, roofing, panels and lighting with skylight glass coming in mid-February.
Interior work continues on all levels on weekdays during regular work hours. Work on the west and south balconies and the east terrace is progressing.
Landscaping on the MBTA path side of the building continues, including the installation of planters and planting soils, which will be followed by lighting. The temporary fence along this path will remain in its current location until the landscaping work is completed.
On the front of the building, the final concrete placement occurred last week. Crews are staging for planter installation. Pavers are being installed into mid-February. Crews are installing conduit for light poles, drainage piping, soil, aeration lines, planting beds, lighting, and curbing along with crushed stone, lighting pathways, and benches. Work will continue to take place around the exterior canopy with panel cladding, caulking, and lighting installation. Below the canopy, curbing is being installed along with ADA sidewalk ramps. The installation of exterior signage will take place late in February into March.
In mid-February, the multi-use walking path connecting the MBTA station to Park Drive will be repositioned closer to the new building. More details will be provided as the date gets closer.
Work on the Atrius Health garage side of the job site is ongoing. Fence posts are being installed next week into early February along with conduit for lighting. New fencing is scheduled to be installed in early 2026.
Work continues on multiple levels inside 421 Park Drive on Saturdays, including Saturday, January 17. Also this Saturday, landscaping work will also be taking place at the southern portion of the site as well as framing and metal panel work at the south jump lobby. There will be a skeleton crew on site on the Martin Luther King Jr. Day holiday.
On weekdays, work is ongoing at the front of the building for the underground garage entrance ramp. The contractor poured a concrete topping slab adjacent to the ramp last week. This work will be followed by the installation of pavers, ramp wall light fixtures, and ramp signage. Work continues on the south jump lobby on several levels and around the Star Market canopy, including lighting, waterproofing, metal panel installation, and pavers below the canopy. On the jump lobby entrance canopy, workers are installing framing, roofing, skylights, panels and lighting.
Interior work continues on all levels on weekdays during regular work hours. Work on the west and south balconies and the east terrace continues. On the east elevation, scaffolding has been erected and crews are installing brick using swing staging.
Landscaping on the MBTA path side of the building continues, including planters and irrigation installation. Installation fence posts, waterproofing the base of the fence posts, and lighting are ongoing. The temporary fence along this path will remain in its current location until the landscaping work is completed.
On the front of the building, additional concrete pours are taking place next week, and pump trucks will be positioned in the area to support these pours. Crews are installing conduit for light poles. Drainage piping, soil, aeration lines, planting beds, lighting, and curbing are being added in this area along with pavers, crushed stone, lighting pathways, and benches. Work will continue to take place around the exterior canopy with panel cladding, caulking, and lighting installation. Below the canopy, curbing is being installed along with ADA sidewalk ramps.
In mid-February, the multi-use walking path connecting the MBTA station to Park Drive will be repositioned closer to the new building. More details will be provided as the date gets closer.
Work on the Atrius Health garage side of the job site is ongoing. Fence posts are being installed along with conduit for lighting. New fencing is scheduled to be installed in early 2026.
Work will continue on multiple levels inside 421 Park Drive on Saturdays, including Saturday, January 10. Also this Saturday, landscaping work will also be taking place at the southern portion of the site as well as framing and metal panel work at the south jump lobby.
On weekdays, work continues at the front of the building for the underground garage ramp with the installation of the snow melt system and waterproofing work. The contractor will also be pouring a concrete topping slab adjacent to the ramp, followed by the installation of pavers, ramp wall light fixtures, and ramp signage. Work will continue on the south jump lobby on several levels and around the Star Market canopy, including lighting, waterproofing, metal panel installation, and pavers below the canopy. On the jump lobby entrance canopy, workers are installing framing, roofing, skylights, panels and lighting.
Interior work continues on all levels on weekdays during regular work hours. Work on the west and south balconies and the east terrace continues. On the east elevation, scaffolding has been erected and crews are installing brick using swing staging into January.
Landscaping on the MBTA path side of the building continues, including planters, and irrigation installation. Installation fence posts, waterproofing, and lighting is ongoing. The temporary fence along this path will remain in its current location until the landscaping work is completed.
On the front of the building, additional concrete pours are scheduled next week, and pump trucks will be positioned in the area to support these pours. Crews are installing conduit for light poles. Drainage piping, soil, aeration lines, planting beds, lighting, and curbing are being added in this area along with crushed stone, lighting pathways, and benches. Work will continue to take place around the exterior canopy with panel cladding, caulking, and lighting installation. In mid-February, the multi-use walking path connecting the MBTA station to Park Drive will be repositioned closer to the new building. More details will be provided as the date gets closer.
Work on the Atrius Health garage side of the job site continues. A topping slab placement at the Fullerton Street corner of the building is scheduled for Monday, January 19. Fence posts are being installed along with conduit for lighting. New fencing is scheduled to be installed in early 2026.
Work will continue on multiple levels inside 421 Park Drive on Saturdays, including Saturday, January 3. Also this Saturday, waterproofing work will be taking place at the garage entry area. Landscaping work will also be taking place at the southern portion of the site as well as along the MBTA path. Framing and metal panel work at the south jump lobby and level 4 canopy will also be taking place.
Monday through Friday, work continues at the front of the building for the underground garage ramp with the installation of the snow melt system and waterproofing work. Work will continue on the south jump lobby on several levels and around the Star Market canopy, including lighting, waterproofing and metal panel installation. Interior work continues on all levels on weekdays during regular work hours. Work on the west and south balconies and the east terrace continues. On the east elevation, scaffolding has been erected and crews are installing brick using swing staging into January.
Landscaping on the MBTA path side of the building continues, including planters, and irrigation installation. Installation of granite curbing is ongoing, along with the installation of fence posts and lighting. The temporary fence along this path will remain in its current location until the landscaping work is completed.
Crews are installing conduit for light poles on the front side of the building. Drainage piping, soil, aeration lines, planting beds, lighting, and curbing are being added in this area along with crushed stone, lighting pathways, and benches. Work will continue to take place around the exterior canopy with panel cladding, caulking, and lighting installation.
Work on the Atrius Health garage side of the job site continues. Fence posts will be installed along with conduit for lighting. Granite curbing is being installed. New fencing is scheduled to be installed in early 2026.
Work will continue on multiple levels inside 421 Park Drive on Saturdays, including Saturday, December 27. Also this Saturday, waterproofing work will be taking place at the garage entry area. Landscaping work will also be taking place at the southern portion of the site as well as along the MBTA path. Framing and metal panel work at the south jump lobby and level 4 canopy will also be taking place.
Monday through Friday, work continues at the front of the building for the underground garage ramp with the installation of the snow melt system and waterproofing work. Work will continue on the south jump lobby on several levels and around the Star Market canopy, including lighting, waterproofing and metal panel installation. Interior work continues on all levels on weekdays during regular work hours. Work on the west and south balconies and the east terrace continues. On the east elevation, scaffolding has been erected and crews are installing brick using swing staging into January.
Landscaping on the MBTA path side of the building continues, including planters, and irrigation installation. Installation of granite curbing is ongoing, and fence posts and lighting are going in over the next several weeks. The temporary fence along this path will remain in its current location until the landscaping work is completed.
Crews are installing conduit for light poles on the front side of the building. Drainage piping, soil, aeration lines, planting beds, lighting, and curbing are being added in this area through the end of the month along with crushed stone, lighting pathways, and benches. Work will continue to take place around the exterior canopy with panel cladding, caulking, and lighting installation.
Work on the Atrius Health garage side of the job site continues. Fence posts will be installed along with conduit for lighting. Granite curbing is being installed. New fencing is scheduled to be installed in early 2026.
The job site will be closed on Thursday, December 25, for the Christmas holiday, and on New Years Day, Thursday, January 1. The 421 Park Drive construction team wishes our neighbors a wonderful holiday!
Work is ongoing on multiple levels inside 421 Park Drive on Saturdays, including Saturday, December 20. Also on Saturday, waterproofing work will be taking place at the garage entry area. Landscaping work will also be taking place at the southern portion of the site as well as along the MBTA path.
Monday through Friday, work continues at the front of the building for the underground garage ramp with the installation of the snow melt system and waterproofing work. Work will continue on the south jump lobby on several levels and around the Star Market canopy, including lighting, waterproofing and metal panel installation. Interior work continues on all levels on weekdays during regular work hours. Work on the west and south balconies and the east terrace continues. On the east elevation, scaffolding has been erected and crews will be installing brick using swing staging into January.
Landscaping on the MBTA path side of the building continues, including planters, and irrigation installation. Installation of granite curbing is ongoing, and fence posts and lighting are going in over the next several weeks. The temporary fence along this path will remain in its current location until the landscaping work is completed.
Crews are installing conduit for light poles on the front side of the building. Drainage piping, soil, aeration lines, planting beds, lighting, and curbing are being added in this area through the end of the month along with crushed stone, lighting pathways, and benches. Work will continue to take place around the exterior canopy with panel cladding, caulking, and lighting installation.
Work on the Atrius Health garage side of the job site continues with temporary walkways shifting periodically to allow for the construction of this sidewalk. Fence posts will be installed along with conduit for lighting. Granite curbing is being installed through next week. New fencing will be delivered in late December.
Work is ongoing on multiple levels inside 421 Park Drive on Saturdays, including Saturday, December 13. Also on Saturday, waterproofing work will be taking place at the garage entry area. Landscaping work will also be taking place at the southern portion of the site as well as along the MBTA path.
Monday through Friday, work continues at the front of the building for the underground garage ramp with the installation of the snow melt system and waterproofing work. Work will continue on the south jump lobby on several levels and around the Star Market canopy, including lighting, waterproofing and metal panel installation. Interior work continues on all levels on weekdays during regular work hours. Work on the west and south balconies and the east terrace continues. On the east elevation, scaffolding has been erected and crews will be installing brick using swing staging into January.
Landscaping on the MBTA path side of the building continues, including planters, and irrigation installation. Installation of granite curbing is ongoing, and fence posts and lighting are going in over the next several weeks. The temporary fence along this path will remain in its current location until the landscaping work is completed.
Crews are installing conduit for light poles on the front side of the building. Drainage piping, soil, aeration lines, planting beds, lighting, and curbing are being added in this area through the end of the month along with crushed stone, lighting pathways, and benches. Work will continue to take place around the exterior canopy with panel cladding, caulking, and lighting installation.
Work on the Atrius Health garage side of the job site continues with temporary walkways shifting periodically to allow for the construction of this sidewalk. Fence posts will be installed along with conduit for lighting. Granite curbing is being installed through next week. New fencing will be delivered in late December.
Work is ongoing on multiple levels inside 421 Park Drive on Saturdays, including Saturday, December 6. Also on Saturday, work will be taking place at the exterior canopy and on the south jump lobby roof. Landscaping work will be taking place on the west balconies as well in the area under the canopy. Roofing and waterproofing work will also be taking place. There will be a boom truck on Fullerton Street on Saturday, December 6, as well. Fullerton Street will remain accessible to vehicles and pedestrians during this work.
A reminder that, unrelated to the 421 Park Drive Project, paving work planned for Miner Street will be taking place on Saturday, December 6, as well.
Monday through Friday, work continues at the front of the building for the underground garage ramp with plans to pour the topping slab mid-December and install ramp wall lighting fixtures. Work will continue on the south jump lobby on several levels and around the Star Market canopy, including lighting and metal panel cladding installation. Crews are excavating along the slurry wall and working on waterproofing. Interior work continues on all levels on weekdays during regular work hours. Installation of fascia panels using swing staging as well as waterproofing during regular daytime work hours continues as well. Work on the west and south balconies and the east terrace continues. On the east elevation, scaffolding has been erected and crews will be installing brick using swing staging into January.
Landscaping on the MBTA path side of the building continues, including oversize paver installation as well as planter, and irrigation installation. Installation of granite curbing is ongoing, and fence posts and lighting are going in over the next several weeks. The temporary fence along this path will remain in its current location until the landscaping work is completed.
Crews are installing pavers on the front side of the building, including under the canopy. Conduit is being installed for light poles. Drainage, soil, aeration lines, planting beds and soil, lighting, and curbing will be added in this area through the end of the month along with crushed stone, lighting pathways, and benches. Work will continue to take place around the exterior canopy with panel cladding and lighting installation.
Work on the Atrius Health garage side of the job site continues with temporary walkways shifting periodically to allow for the construction of this sidewalk. Fence posts will be installed along with conduit for lighting. Granite curbing is being installed into next week. New fencing will be delivered in late December.
We use cookies to analyze website traffic and optimize your website experience. By accepting our use of cookies, your data will be aggregated with all other user data.