Standard work hours for project construction are Monday - Friday, 7:00 a.m. to 5:00 p.m. Some select, less intensive activities may need to occur on Saturdays from 8:00 a.m. to 5:00 p.m. Extended hours may be required for select activities. The contractor will strive to keep these instances to a minimum and abutters will be notified in advance.
Check back here for upcoming construction updates for 421 Park Drive. If you have any questions or concerns, please contact us at construction@421parkdr.com.
Work continues on various levels inside the building at 421 Park Drive on Saturdays, including this Saturday, August 30. The work site will be closed on Monday, September 1, for the Labor Day holiday.
Form work is ongoing at the front of the building for the underground garage ramp, to be followed by rebar installation.
Interior work continues on all levels on weekdays during regular work hours. Work will continue to install fascia panels using swing staging as well as waterproofing work during second shift (2:00 p.m. to 10:00 p.m.). This work is quiet and should not be noticeable to the surrounding community.
Roof installation continues working from the north portion of the building to the south.
There will be a crane on Fullerton Street each day from Wednesday, September 3, through Friday, September 5, from 7am to 5pm and later in the month on Wednesday and Thursday, September 17 and 18. Fullerton Street will remain accessible to vehicles and pedestrians during this work.
Landscaping on the MBTA path side of the building continues, including planter and paver installation. The temporary fence along this path has been shifted west and will remain in this location through October while landscaping work along the path is completed. From mid-September through the end of October, the contractor will be excavating on the MBTA side of the building and filling the area with soil.
Landscaping work on the Atrius Health garage side of the job site is expected to take place until mid-to-late September. Currently, a new walkway is being poured across from the Atrius Health garage to run along Miner Street. This week and next, pedestrians are being re-routed to the garage side of Miner Street to accommodate construction of the new sidewalk.
Finally, there’s another week or two of work planned in front of REI.
Work continues on various levels inside the building at 421 Park Drive on Saturdays, including this Saturday, August 23. In addition, this Saturday, August 23, the walkway across from the Atrius Health garage will be re-positioned to run along the job site fencing to allow landscaping work to continue.
Most importantly this weekend, a notice went out to the community yesterday describing the crane operation planned for Saturday and Sunday to hoist generators to the roof. After consulting with the Boston Transportation Department (BTD), the City required some timing and logistics changes to the contractor’s plans as follows:
Work to install curtain wall on the building’s west elevation is complete and the contractor will be installing an air vapor barrier (AVB) at this location early next week.
Interior work continues on all levels on weekdays during regular work hours. Work will continue to install fascia panels using swing staging as well as waterproofing work during second shift (2:00 p.m. to 10:00 p.m.). This work is quiet and should not be noticeable to the surrounding community.
Roof installation continues working from the north portion of the building to the south. The contractor is also installing planters and soils on the MBTA path side of the building using a crane.
There will be a crane on Fullerton Street each day from Wednesday, August 27, through Friday, August 29 from 7am to 5pm. Fullerton Street will remain accessible to vehicles and pedestrians during this work.
Landscaping on the MBTA path side of the building continues. The temporary fence along this path has been shifted west and will remain in this location through October while landscaping work along the path is completed.
Landscaping work on the Atrius Health garage side of the job site is expected to take place until mid-to-late September. To accommodate pedestrian traffic during this time to and from Brookline Ave, a new temporary walkway is in place on the construction side of the street. As noted above, on Saturday, August 23, the walkway will be re-positioned to run along the job site fencing opposite the Atrius Health garage to allow landscaping work to continue. On Monday, August 25, pedestrians will be re-routed to a temporary path on the garage side of Miner Street to accommodate a concrete pour of for the sidewalk between 7am and 9am. Some saw cutting on the sidewalk will take place on Tuesday and Wednesday, August 26 and 27.
In recent communications, it was noted the contractor at 421 Park Drive would be positioning a crane on Fullerton Street this weekend to hoist generators and other materials to the penthouse level of the building from 8am to 8pm on both Saturday and Sunday. After consulting with the Boston Transportation Department (BTD), there are some time and logistics changes to this work that are required by the City, and we want to share them for your awareness.
Per BTD, the contractor is required to maintain two lanes of traffic on Fullerton Street during this operation so the road and sidewalks will remain accessible to vehicles and pedestrians during this work.
In order to keep Fullerton open, the crane will need to block two of the three lanes into the 401 Park Drive garage. Once the crane’s boom is erected on Saturday by roughly 6am, the two blocked entrances to the garage will be available to the public. The two lanes will then be closed again on Sunday from 4am to 8am while the boom is removed. There is a possibility, if all of the hoists go as planned, that removal of the boom can happen between 12pm and 2pm on Saturday. If so, the garage lanes would be closed during that timeframe and there will be one exit/entrance lane open at the garage entrance.
Neighbors can expect some intermittent noise from the truck deliveries and presence of crews during the hours noted. Some lighting on the Fullerton Street side of the job site will also be needed to support this work as well. The contractor will do everything possible to minimize the impact of this crane operation on the community.
The project team is appreciative of the neighborhood's patience and cooperation during this necessary work. The community will be pleased to know that this is expected to be the project’s final weekend after-hours crane operation.
Work continues on various levels inside the building at 421 Park Drive on Saturdays, including this Saturday, August 16. In addition, a crane will be on site at the building’s south lobby entrance installing curtainwall (see additional detail on this activity below). Work will also take place on the balconies of the building, including levels 4 and 8.
Work to install curtain wall on the building’s south lobby area and the west elevation began last week. To support curtain wall work, a crane is positioned at the front of the building through Tuesday, August 19.
Interior work continues on all levels on weekdays during regular work hours. The painters who have been working second shift (2:00 p.m. to 10:00 p.m.) on the exterior of the building are finished, however, work will continue to install fascia panels using swing staging as well as waterproofing work during second shift. This work is quiet and should not be noticeable to the surrounding community.
Roof installation continues working from the north portion of the building to the south. The contractor is also installing soils on the MBTA path side of the building using a crane during the week of August 18.
Landscaping on the MBTA path side of the building has started. The temporary fence along this path has been shifted west and will remain in this location through October while landscaping work along the path is completed.
A crane will be on Fullerton Street again on Saturday and Sunday, August 23-24, from 8am to 8pm both days, to hoist generators to the penthouse. Fullerton Street will remain accessible to vehicles and pedestrians during this work. There will also be a crane on the Fullerton Street side of the building from 7am to 5pm on Wednesday, August 27, through Friday, August 29.
The job site fence on the Atrius Health garage side of the job site has shifted to accommodate new landscaping. Landscaping work in this area is expected to take place until mid-to-late September. To accommodate pedestrian traffic during this time to and from Brookline Ave a new temporary walkway is in place on the construction side of the street, with fencing in place on both sides of the path.
On Saturday, August 23, the walkway will be re-positioned to run along the job site fencing opposite the Atrius Health garage to allow landscaping work to continue.
Work continues on various levels inside the building at 421 Park Drive on Saturdays, including this Saturday, August 9. In addition, a crane will be on site at the southwest corner of the building to hoist materials to the balcony areas as well as work at the building’s south lobby entrance, including framing and roofing work.
Work to install curtain wall on the building’s south lobby area will begin next week. To support curtain wall work, a crane will be positioned at the front of the building from Wednesday, August 13, through Tuesday, August 19. Concrete work is ongoing at the front of the building for the underground garage ramp.
Interior work continues on all levels on weekdays during regular work hours. The painters that have been working second shift (2:00 p.m. to 10:00 p.m.) on the exterior of the building are finished, however, work will continue to install fascia panels using swing staging as well as waterproofing work during second shift. This work is quiet and should not be noticeable to the surrounding community.
Roof installation continues working from the north portion of the building to the south. The contractor will be installing soils next week on the MBTA path side of the building using a crane.
There will be a crane on the Fullerton Street side of the building from 7am to 3pm on Wednesday, August 13, Thursday, August 14, and Friday, August 15. Fullerton Street will remain accessible to vehicles and pedestrians during this work. A crane will be on Fullerton Street again on Saturday and Sunday, August 23-24, from 8am to 8pm both days, to hoist a generator to the penthouse.
Landscaping on the MBTA path side of the building has started. The temporary fence along this path has been shifted west and will remain in this location through October while landscaping work along the path is completed.
The job site fence on the Atrius Health garage side of the job site has shifted to accommodate new landscaping. Landscaping work in this area is expected to take place until mid-to-late September. To accommodate pedestrian traffic during this time to and from Brookline Ave a new temporary walkway has been created. Currently, the temporary walkway is located on the construction side of the street, with fencing in place on both sides of the path. We anticipate that this walkway will be in place through the end of August, at which point, the walkway will be re-positioned to run along the job site fencing opposite the Atrius Health garage to allow landscaping work to continue.
Work continues on various levels inside the building at 421 Park Drive on Saturdays, including this Saturday, August 2. In addition, work will be taking place on Saturday at the building’s south lobby entrance, including framing and roofing work.
Concrete work is ongoing at the front of the building for the underground garage ramp.
Interior work continues on all levels on weekdays during regular work hours. Painters continue to work on second shift (2:00 p.m. to 10:00 p.m.) on the exterior of the building along with a subcontractor installing fascia panels. This is quiet work and should not be noticeable to the surrounding community.
Roof installation continues working from the north portion of the building to the south.
Landscaping on the MBTA path side of the building began last week. The temporary fence along this path has been shifted west and will remain in this location through October while landscaping work along the path is completed. A crane will be used on Tuesday, August 5 (7 am - 3 pm), through Saturday, August 9 (8 am - 4 pm), to hoist materials to the 4th floor.
Work to install curtain wall on the building’s south lobby area will begin starting the week of August 11.
There will be a crane on the Fullerton Street side of the building from 7 am to 3 pm Thursday, August 7, and Friday, August 8. Fullerton Street will remain accessible to vehicles and pedestrians during this work. The following week, a crane can be expected in this area Wednesday, August 13, through Friday, August 15, from 7 am to 3 pm. A crane is also scheduled for the Fullerton Street side of the building for two days at the end of August to hoist a generator to the roof.
The job site fence on the Atrius Health garage side of the job site has shifted to accommodate new landscaping. Landscaping work in this area is expected to take place until mid-to-late September. To accommodate pedestrian traffic during this time to and from Brookline Ave a new temporary walkway has been created. Currently, the temporary walkway is located on the construction side of the street, with fencing in place on both sides of the path. We anticipate that this walkway will be in place through the end of August, at which point, the walkway will be re-positioned to run along the job site fencing opposite the Atrius Health garage to allow landscaping work to continue.
Work continues on various levels inside the building at 421 Park Drive on Saturdays, including this Saturday, July 26. A crane will be in use on Saturday to install planters on the MBTA path side of the building. In addition, landscaping work will be taking place in the fenced area at the south side of 401 Park Drive. There will also be a crane removing bracing at the new garage entrance ramp on south side of the building and roofing work, spray on fireproofing, and concrete work at the newly erected elevator lobby.
Excavation and bracing installation are ongoing on the front of the building for the underground garage ramp. This work is expected to take a few more weeks and may generate some noise during the day.
Interior work continues on all levels on weekdays during regular work hours. Painters continue to work on second shift (2:00 p.m. to 10:00 p.m.) on the exterior of the building along with a subcontractor installing fascia panels. This is quiet work and should not be noticeable to the surrounding community.
Roof installation has started working from the north portion of the building to the south.
There will be a crane on the Fullerton Street side of the building from 7am to 5pm Thursday, August 7, and Friday, August 8. Fullerton Street will remain accessible to vehicles and pedestrians during this work.
The job site fence on the Atrius Health garage side of the job site has shifted to accommodate new landscaping. This work is expected to last until mid-to-late September. To accommodate pedestrian traffic during this time and ensure foot access to and from Brookline Ave is maintained, the old sidewalk was demolished, and a new temporary walkway is being created in a few phases.
Currently, the temporary walkway is located on the construction side of the street, with fencing in place on both sides of the path. We anticipate that this work will extend through the end of August, at which point, the walkway will be re-positioned to run along the job site fencing opposite the Atrius Health garage to allow landscaping work to continue.
Landscaping on the MBTA path side of the building began last week. In addition, as noted above, a crane will be used here to install planters on Saturday, July 26, and Monday and Tuesday, July 28 and 29.
Work to install curtain wall on the building’s south lobby area is targeted to begin on or about Thursday, August 7.
Work continues on various levels inside the building at 421 Park Drive on Saturdays, including this Saturday, July 19. In addition, landscaping work will taking place in the fenced area at the south side of 401 Park Drive.
Excavation and bracing installation are ongoing on the front of the building for the underground garage ramp. This work is expected to take a few more weeks and may generate some noise during the day.
Interior work continues on all levels on weekdays during regular work hours. Painters continue to work on second shift (2:00 p.m. to 10:00 p.m.) on the exterior of the building along with a subcontractor installing fascia panels. This is quiet work and should not be noticeable to the surrounding community.
Roof installation began last week working from the north portion of the building to the south.
There will be a crane on the Fullerton Street side of the building from 7am to 5pm Tuesday, July 29 through Thursday, July 31. Fullerton Street will remain accessible to vehicles and pedestrians during this work.
The job site fence on the Atrius Health garage side of the job site has shifted to accommodate new landscaping. This work is expected to last until mid-to-late September. To accommodate pedestrian traffic during this time and ensure foot access to and from Brookline Ave is maintained, the old sidewalk was demolished, and a new temporary walkway is being created in a few phases.
Currently, the temporary walkway is located on the construction side of the street, with fencing in place on both sides of the path. We anticipate that this work will extend through the end of August, at which point, the walkway will be re-positioned to run along the job site fencing opposite the Atrius Health garage to allow landscaping work to continue.
Landscaping on the MBTA path side of the building is scheduled to begin the week of 7/21. In addition, a crane will be used here to install planters on Saturday, July 26, and Monday and Tuesday, July 28 and 29.
Work to install curtain wall on the building’s south lobby area is targeted to begin on or about Thursday, August 7.
Work continues on various levels inside the building at 421 Park Drive on Saturdays, including this Saturday, July 12. There will also be a crane on the Fullerton Street side of the building on Saturday beginning at 8am to hoist pergola steel up to the 4th floor. In addition, excavation for utilities and waterproofing work will be taking place at the south portion of the building.
Excavation and bracing installation are ongoing on the front of the building for the underground garage ramp. This work is expected to take a few more weeks and may generate some noise during the day.
Interior work continues on all levels on weekdays during regular work hours. Painters continue to work on second shift (2:00 p.m. to 10:00 p.m.) on the exterior of the building along with a subcontractor installing fascia panels. This is quiet work and should not be noticeable to the surrounding community.
Roof installation began last week working from the north portion of the building to the south.
There will be a crane on the Fullerton Street side of the building from 7am to 5pm Wednesday, July 16 through Friday, July 18. Fullerton Street will remain accessible to vehicles and pedestrians during this work.
The job site fence on the Atrius Health garage side of the job site has shifted to accommodate new landscaping. This work is expected to last until mid to late- September. To accommodate pedestrian traffic during this time and ensure foot access to and from Brookline Ave is maintained, the old sidewalk has been demolished, and a new temporary walkway is being created in a few phases.
Currently, the temporary walkway is located on the construction side of the street, with fencing in place on both sides of the path. This configuration will be in place for about one month. Then, by mid-July, while landscaping continues, the walkway will be re-positioned to run along the job site fencing opposite the Atrius Health garage.
Landscaping on the MBTA path side of the building is scheduled to begin in mid-July. Work to install curtain wall on the building’s south lobby area is targeted to begin on or about Thursday, August 7.
Work continues on various levels inside the building at 421 Park Drive on Saturdays, including this Saturday, July 5.
As a reminder, the job site will be closed on Friday, July 4, for the holiday.
Excavation and bracing installation are ongoing on the front of the building for the underground garage ramp. This work is expected to take a few more weeks and may generate some noise during the day.
Interior work continues on all levels on weekdays during regular work hours. Painters continue to work on second shift (2:00 p.m. to 10:00 p.m.) on the exterior of the building along with a subcontractor installing fascia panels. This is quiet work and should not be noticeable to the surrounding community.
Roof installation is anticipated to begin on Monday, July 7, in phases, working from the north portion of the building to the south. Also starting on Monday, July 7, a crew will be working 4pm to midnight through Friday, July 11, to remove the Bright Horizons playground located on the 401 Park side of the building. This work area is contained between the new building and 401 Park, which should help with noise mitigation.
There will be a crane on the Fullerton Street side of the building on the following days from 7am to 5pm – Tuesday, July 8 through Thursday, July 10. Fullerton Street will remain accessible to vehicles and pedestrians during this work.
Work to install curtain wall on the building’s south lobby area is targeted to begin on or about Friday, July 25.
The job site fence on the Atrius Health garage side of the job site has shifted to accommodate new landscaping. This work is expected to last until mid to late- September. To accommodate pedestrian traffic during this time and ensure foot access to and from Brookline Ave is maintained, the old sidewalk is being demolished, and a new temporary walkway is being created in a few phases.
Currently, the temporary walkway is located on the construction side of the street, with fencing in place on both sides of the path. This configuration will be in place for about one month. Then, by mid-July, while landscaping continues, the walkway will be re-positioned to run along the job site fencing opposite the Atrius Health garage.
Landscaping on the MBTA path side of the building is scheduled to begin in late July.
Work continues on various levels inside the building at 421 Park Drive on Saturdays, including this Saturday, June 28. Workers will also be moving steel on Saturday using a small crane at the south portion of the building. Roofing and ceiling metal panel work is also expected to take place on the fourth level of the building.
The job site will be closed on Friday, July 4, for the holiday.
Excavation and bracing installation are ongoing on the front of the building for the underground garage ramp. This work is expected to take a few more weeks and may generate some noise during the day.
Interior work continues on all levels on weekdays during regular work hours. Painters continue to work on second shift (2:00 p.m. to 10:00 p.m.) on the exterior of the building along with a subcontractor installing fascia panels. This is quiet work and should not be noticeable to the surrounding community.
Roof installation is anticipated to begin on Monday, July 7, in phases, working from the North portion of the building to the south.
There will be a crane on the Fullerton Street side of the building on the following days from 7am to 5pm –Tuesday, July 1 through Thursday, July 3, and Tuesday, July 8 through Thursday, July 10. Fullerton Street will remain accessible to vehicles and pedestrians during this work.
The new Star Market canopy is now scheduled to be installed on Saturday, July 19, using a crane.
Work to install curtain wall on the building’s south lobby area is targeted to begin on or about Friday, July 25.
The job site fence on the Atrius Health garage side of the job site has shifted to accommodate new landscaping. This work is expected to last until mid to late- September. To accommodate pedestrian traffic during this time and ensure foot access to and from Brookline Ave is maintained, the old sidewalk is being demolished, and a new temporary walkway is being created in a few phases.
Currently, the temporary walkway is located on the construction side of the street, with fencing in place on both sides of the path. This configuration will be in place for about one month. Then, by mid-July, while landscaping continues, the walkway will be re-positioned to run along the job site fencing opposite the Atrius Health garage.
Landscaping on the MBTA path side of the building is scheduled to begin in late July.
Work continues on various levels inside the building at 421 Park Drive on Saturdays, including this Saturday, June 21. Workers will be on swing staging on the west portion of the building. In addition, there will be a crane in front of 401 Park Drive unrelated to the 421 project.
Excavation and bracing installation are ongoing on the front of the building for the underground garage ramp. This work is expected to take about four weeks and may generate some noise during the day.
Interior work continues on all levels on weekdays during regular work hours. Painters continue to work second shift (3:00 p.m. to 11:00 p.m.) on the exterior of the building and are nearing completion. Roof installation begins at the end of June in phases, working from the back of the building to the front.
There will be a crane on the Fullerton Street side of the building on the following days from 7am to 5pm – Wednesday, June 25, Thursday, June 26, and Tuesday, July 1 through Thursday, July 3. Fullerton Street will remain accessible to vehicles and pedestrians during this work.
The contractor has shifted the job site fence on the Atrius Health garage side of the job site to accommodate new landscaping. This work is expected to last until mid to late- September. To accommodate pedestrian traffic during this time and ensure foot access to and from Brookline Ave is maintained, the old sidewalk is being demolished, and a new temporary walkway is being created in a few phases.
Currently, the temporary walkway is located on the construction side of the street, with fencing in place on both sides of the path. This configuration will be in place for about one month. Then, by early July, while landscaping continues, the walkway will be re-positioned to run along the job site fencing opposite the Atrius Health garage.
The new Beacon Street crosswalk at Miner Street can move forward once Eversource makes its necessary electrical connections, after which the area will be restriped. The neighborhood’s ongoing patience with this project is appreciated.
Work continues on various levels inside the building on Saturdays, including this Saturday, June 14. Also this Saturday, workers will be installing steel at the south entrance canopy with a crane. Scaffolding removal at the west terrace on level 4 will also be taking place.
A crane will be in use in front of the building next week for two to three days to install stairs.
On Monday, June 16, excavating and bracing installation will continue for the underground garage ramp on the front of the building. This work is expected to take about four weeks and may generate some noise during the day.
There will be a crane on the Fullerton Street side of the building on Wednesday, June 18, from 7am to 5pm. Fullerton Street will remain accessible to vehicles and pedestrians.
The canopy steel over the new Star Market entrance will be installed on Saturday, June 21, with a crane.
Interior work is ongoing on all levels on weekdays during regular work hours.
Painters continue to work second shift (3:00 p.m. to 11:00 p.m.) on the exterior of the building and are nearing completion. Roof installation begins at the end of June in phases, working from the back of the building to the front.
The contractor has shifted the job site fence on the Atrius Health garage side of the job site to accommodate new landscaping. This work is expected to last until mid to late- September. To accommodate pedestrian traffic during this time and ensure foot access to and from Brookline Ave is maintained, the old sidewalk is being demolished, and a new temporary walkway is being created in a few phases. Currently, the temporary walkway is located on the construction side of the street, with fencing in place on both sides of the path. This configuration will be in place for about one month. Then, by early July, while landscaping continues, the walkway will be re-positioned to run along the job site fencing across from the Atrius Health garage.
The new Beacon Street crosswalk at Miner Street can move forward once Eversource makes its necessary electrical connections, after which the area will be restriped. The neighborhood’s ongoing patience with this project is appreciated.
Work continues on Saturdays on various levels inside the building, including this Saturday, June 7. Also this Saturday, some steel workers will be doing some welding on the front of the building. The crane will not be needed for this work.
A crane will be in use in front of the building next week for two days to install stairs.
On Monday, June 9, the contractor will begin excavating for the underground garage ramp on the front of the building. This work is expected to take about four days and will generate some noise.
The canopy steel over the new Star Market entrance will be installed on Saturday, June 14.
Interior work is ongoing on all levels on weekdays during regular work hours.
Painters continue to work second shift (3:00 p.m. to 11:00 p.m.) on the exterior of the building and are nearing completion. Swing staging is in use on the side of the building facing the neighborhood to support this work, which is not inherently noisy.
The contractor has shifted the job site fence on the Atrius Health garage side of the jobsite several feet out to accommodate new landscaping. This work is expected to last until mid- September. To accommodate pedestrian traffic during this time and ensure foot access to and from Brookline Ave is maintained, the old sidewalk is being demolished, and a new temporary walkway is being created in a few phases. Currently, the temporary walkway is located on the construction side of the street, with fencing in place on both sides of the path. This configuration will be in place for about one month. Then, by early July, while landscaping continues, the walkway will be re-positioned to run along the job site fencing across from the Atrius Health garage.
Workers continue water testing the curtain wall on several levels on the Atrius side and Miner Street corner of the building using boom lifts. Please note that it’s possible neighbors may experience some overspray during this work.
Eversource has finished its work installing cables and conduit inside the manholes along Fullerton Street.
The new Beacon Street crosswalk at Miner Street can move forward once Eversource makes its necessary electrical connections, after which the area will be restriped. The neighborhood’s ongoing patience with this project is appreciated.
The contractor at 421 Park Drive will continue to work on various levels inside the building on Saturdays, including this Saturday, May 31. No additional work is planned for this Saturday. Interior work is ongoing on all levels on weekdays during regular work hours.
Steel installation was finished last week. Painters continue to work second shift (3:00 p.m. to 11:00 p.m.) on the exterior of the building for the next several weeks. Swing staging is in use on the side of the building facing the neighborhood to support this work, which is not inherently noisy. After dark, the crew uses the existing building lights supplemented by head lamps to get the work done.
A crane is in use in front of the building installing curtain wall, which will continue into next week. In mid to late June, Suffolk will start excavating for the underground garage.
There will be crane on the Fullerton Street side up against the building on Wednesday, June 4, from 7am to 5pm to lift materials to upper levels. Fullerton Street will not be impacted.
Last week, the contractor began shifting the job site fence across from the Atrius Health garage several feet out to accommodate new landscaping. This work is expected to last until September 15. To accommodate pedestrian traffic during this time, a new temporary walkway will be created in a few phases to ensure foot access to and from Brookline Ave is maintained. Beginning on Monday, June 2, the walkway will be located on the 421 Park side of the street, with fencing in place on both sides of the path. This temporary walkway will be in place for about one month. Then, by July 4, while landscaping continues, the walkway will be positioned to run along the job site fencing across from the Atrius Health garage.
During the week of June 2, workers will be water testing the curtain wall on several levels on the Atrius side and Miner Street corner of the building using boom lifts. Please note that it’s possible neighbors may experience some overspray during this work.
The canopy steel over the new Star Market entrance will be installed on Saturday, June 14.
The new Beacon Street crosswalk at Miner Street can move forward once Eversource makes its necessary electrical connections, after which the area will be restriped. The neighborhood’s ongoing patience with this project is appreciated.
National Grid is installing cables and conduit inside the manholes along Fullerton Street. This work is expected to continue into early June. Vehicle and pedestrian access to Fullerton Street is fully maintained during this week.
As always, work at 421 Park Drive will continue to take place on various levels inside the building on Saturdays, including this Saturday, May 24. Also this Saturday, the contractor is planning to install steel using a crane on the front of the building. The steel work is generally not a noisy operation, however, neighbors can expect to see crew members on site and hear some work taking place on Saturday.
The job site will be closed for the Memorial Day holiday on Monday, May 26.
Steel installation will be finished by Tuesday, May 27. Painters continue to work second shift (3:00 p.m. to 11:00 p.m.) on the exterior of the building for the next several weeks. Swing staging is in use on the side of the building facing the neighborhood to support this work, which is not inherently noisy. After dark, the crew uses the existing building lights supplemented by head lamps to get the work done.
Interior work is ongoing on all levels on weekdays during regular work hours.
A crane is in use on site to install curtain wall, which will continue through May 29 in two locations – the corner of the building closet to the MBTA and in front on the Park Drive side of the building.
Beginning on Tuesday, May 27, the contractor will begin shifting the job site fence along Miner Street several feet out to accommodate new landscaping. This work is expected to last until September 15. To accommodate pedestrian traffic during this time, a new temporary walkway will be created in three phases to ensure foot access to and from Brookline Ave is maintained. During the week of May 27, a temporary walkway will be built on the Atrius Health side of Miner Street for use through May 31. Then, beginning on June 1, the walkway will shift back to the construction side of the street, where fencing will be in place on both sides of the path. Finally, by July 4, the walkway will shift back adjacent to the job site fencing along Miner Street.
During the week of June 2, workers will be water testing the curtain wall on several levels on the Atrius side and Miner Street corner of the building using boom lifts. Please note that it’s possible neighbors may experience some overspray during this work.
The new Beacon Street crosswalk at Miner Street can move forward once Eversource makes its necessary electrical connections, after which the area will be restriped. The neighborhood’s ongoing patience with this project is appreciated.
National Grid can be seen installing cables and conduit along Fullerton Street. This work is expected to continue through mid-June.
As always, work at 421 Park Drive will continue to take place on various levels inside the building on Saturdays, including this Saturday, May 17. Also this Saturday, the contractor is planning to install steel using a crane on the front of the building. The steel work is generally not a noisy operation, however, neighbors can expect to see crew members on site and hear some work taking place on Saturday.
Painters continue to work second shift (3:00 p.m. to 11:00 p.m.) on the exterior of the building for the next six weeks. Abutters will notice workers using swing staging on the side of the building facing the neighborhood. This work is not inherently noisy, and, after dark, the crew will only use the existing building lights supplemented by head lamps to get the work done.
Interior work is ongoing on all levels on weekdays during regular work hours.
The car stacker for the new underground garage arrived on site last week. Also last week, a crane arrived on site to install steel through Thursday, May 22. A second crane was delivered to the site to install curtain wall, which began on May 15 and is scheduled through May 29 in two locations – first on the on corner of the building closet to the MBTA and then the crane will move out front to the Park Drive side of the building.
Beginning on Monday, June 2, the job site fence line along Miner Street will be extended out several feet over the current pedestrian walkway to accommodate new landscaping. A new temporary walkway will be created to ensure that pedestrian access to and from Brookline Ave is maintained. This set up is expected to last until September 15.
The new Beacon Street crosswalk at Miner Street can move forward once Eversource makes its necessary electrical connections, after which the area will be restriped. The neighborhood’s ongoing patience with this project is appreciated.
Both Eversource and National Grid can be seen installing cables and conduit along Fullerton Street. This work is expected to continue through mid-June.
We use cookies to analyze website traffic and optimize your website experience. By accepting our use of cookies, your data will be aggregated with all other user data.